SA 300: planning an audit, and why the strategy comes before the plan

What SA 300 actually requires before fieldwork starts — the overall strategy, the detailed plan that follows it, and why planning is a continuous activity revised throughout the engagement, not a one-time document.

SA 300 requires the auditor to establish an overall audit strategy before developing a detailed audit plan — two distinct outputs, deliberately kept separate, because they answer different questions. The strategy sets the scope, timing and direction of the audit at a high level: which locations, which reporting framework, how materiality will be approached, where the significant risks are expected to lie. The plan translates that strategy into specifics: the nature, timing and extent of risk assessment procedures and further audit procedures, and who on the team will perform them. Planning is not finished once this is written — SA 300 explicitly requires it to be updated as the audit progresses and new information emerges.

What the strategy actually has to establish

  1. 01Characteristics of the engagement that define its scopeThe applicable financial reporting framework, industry-specific reporting requirements, the number of locations, and whether component auditors are involved.
  2. 02Reporting objectives, timing and required communicationsThe deadline for the audit opinion, interim reporting requirements if any, and planned communications with management and those charged with governance.
  3. 03Factors significant in directing the team's effortsPreliminary materiality, areas with higher assessed risk from prior experience or current knowledge, and the involvement of experts if any are expected to be needed.

Why the plan is a separate, more detailed document

Strategy vs. plan
Audit strategyAudit plan
Level of detailHigh level — scope, approach, resourcingDetailed — specific procedures, by whom, by when
When it's setEarly, often before detailed risk assessment is completeDeveloped from the strategy, informed by the risk assessment under SA 315
Typical contentEngagement scope, reporting timetable, preliminary risk areas, resource allocationNature, timing and extent of risk assessment procedures, and of further audit procedures at the assertion level
Strategy vs. plan

Common practice, not a requirement

A plan written before the strategy decisions that should inform it — scope, preliminary materiality, where resources will go — tends to read as a generic procedure list rather than a document genuinely shaped by this engagement's specific risk profile, which is exactly the gap SA 300's two-step sequence is meant to prevent.

Why planning doesn't stop once fieldwork starts

SA 300 explicitly treats planning as a continuous, iterative process. A risk identified mid-fieldwork, an unexpected finding, or a change in the entity's circumstances should feed back into the strategy and plan, with the changes documented — not absorbed informally into whatever testing happens to follow. A planning memo that was accurate in week one but was never revisited as the engagement's understanding deepened is, by the end of fieldwork, describing an audit that no longer matches the one actually performed.

This is practical guidance written for audit teams, not an authoritative statement of any standard or statute. Standards, forms and timelines change. Check the current text issued by the ICAI and the relevant authority before relying on anything here in an audit file.